Pedestrian Plan Phase II Update- June 14, 2019

On Tuesday, June 11th, RPC Contracting poured the final sections of concrete at the Soundside Shoppes, Osprey Landing, Town Hall, and Kellogg Supply Company to complete the sidewalk construction project. On Wednesday, VHB Engineering and Town of Duck officials walked the entire project with RPC representatives to inspect the work completed and develop a punch-list […]

Read More

Pedestrian Plan Phase II Update- May 17, 2019

Over the past week, RPC Contracting continued grading and installation of the stone base in the remaining portions of the project before pouring sidewalks. On Friday, RPC will begin installation of formwork for the sidewalks and replacement stairway at Soundfeet Shoes/Ocean Atlantic Rentals. During the week of May 20th, RPC will continue the formwork and […]

Read More

Pedestrian Plan Phase II Update- April 5, 2019

The past week saw no progress toward construction of the planned sidewalk as Dominion Energy completed preparations for moving several underground lines. The upcoming week (beginning 4/8) will see more substantial progress.  RPC Contracting will begin grading for the sidewalk at Aqua Restaurant & Spa and work northward to Super Wings over the next few […]

Read More

Pedestrian Plan Phase II Update- March 1, 2019

In spite of rainy weather, RPC Contracting was able to make progress on the new sidewalk along the west side of Duck Village over the past week.  RPC poured sidewalks in the stretch from Nags Head Hammocks to the northern entrance of the Town Park by the playground.  They also graded, formed, and laid the […]

Read More

Pedestrian Plan Phase II Update- February 8, 2019

Over the past week, the project really began to take shape as RPC Contracting began to pour the sidewalk.  RRP poured most of the sidewalk from Resort Realty at the northern end of the project through the southern entrance to the Waterfront Shops.   New driveways were poured at Wee Winks Square, the southern entrance to […]

Read More