Pedestrian Plan Phase II Update- February 8, 2019

Over the past week, the project really began to take shape as RPC Contracting began to pour the sidewalk.  RRP poured most of the sidewalk from Resort Realty at the northern end of the project through the southern entrance to the Waterfront Shops.   New driveways were poured at Wee Winks Square, the southern entrance to […]

Read More

Pedestrian Plan Phase II Update- December 28, 2018

The past week saw additional construction activity on the pedestrian improvements through Duck Village despite the holiday. RPC Contracting continued grading and began saw cutting in the northern half of the project area. Millstone Marine Construction has nearly completed construction of a retaining wall by the northern end of the Duck United Methodist Church property […]

Read More

Pedestrian Plan Phase II Update- December 7, 2018

Over the past week, RPC Contracting continued initial grading in the area near the Waterfront Shops and Dare County water tower. RPC Contracting will continue with initial grading of the sidewalk corridor next week moving south of the water tower.  Millstone Marine may begin construction of several bulkheads along the path of the sidewalk.  Due […]

Read More

Pedestrian Plan Phase II Update- November 30, 2018

Over the past week, RPC Contracting completed initial grading from the northern end of the project area (Resort Realty) extending southward to the Dare County water tower. RPC Contracting will continue with initial grading of the sidewalk corridor next week moving south of the water tower. Due to the use of heavy equipment, the southbound […]

Read More

Pedestrian Plan Update – May 4, 2018

The first phase of pedestrian improvements along the east side of Duck Road (N.C. Highway 12) in Duck Village is close to completion.  Over the past week, Barnhill Contracting completed dozens of items on its punch list.  Significant projects included reconstruction of curbing by Kellogg Hardware’s parking area, raising and reworking a segment of sidewalk […]

Read More

Pedestrian Plan Update- April 27, 2018

The first phase of pedestrian improvements along the east side of Duck Road (N.C. Highway 12) in Duck Village is close to completion. Over the past week, Barnhill Contracting completed much of the final grading in preparation for landscaping around the sidewalk. They also completed construction of the two landscaped medians in the center lane […]

Read More

Pedestrian Plan Update- April 20, 2018

The first phase of pedestrian improvements along the east side of Duck Road (N.C. Highway 12) in Duck Village is nearing completion. Over the past week, Barnhill Contracting completed grading around the sidewalk and began construction of the two landscaped gateway medians in the center lane of Duck Road. These medians are intended to be […]

Read More

Pedestrian Plan Update- April 13, 2018

The first phase of pedestrian improvements along the east side of Duck Road (N.C. Highway 12) in Duck Village is nearing completion. After limiting construction activities for a couple of weeks over Spring Break and the Easter holiday, Barnhill Contracting has renewed its efforts to complete the project by May 15th. Barnhill is presently repairing […]

Read More

Pedestrian Plan Update- March 16, 2018

Construction on Phase I of the Town of Duck Comprehensive Pedestrian Plan along the east side of Duck Road (N.C. Highway 12) in Duck Village continues making progress. Over the past week Barnhill Contracting poured concrete for the new driveway entrances and sidewalks. The short stretches of sidewalk connecting the northern end of the project […]

Read More