Pedestrian Plan Phase II Update- December 7, 2018

Over the past week, RPC Contracting continued initial grading in the area near the Waterfront Shops and Dare County water tower. RPC Contracting will continue with initial grading of the sidewalk corridor next week moving south of the water tower.  Millstone Marine may begin construction of several bulkheads along the path of the sidewalk.  Due […]

Read More

Pedestrian Plan Phase II Update- November 30, 2018

Over the past week, RPC Contracting completed initial grading from the northern end of the project area (Resort Realty) extending southward to the Dare County water tower. RPC Contracting will continue with initial grading of the sidewalk corridor next week moving south of the water tower. Due to the use of heavy equipment, the southbound […]

Read More

Pedestrian Plan Phase II Update- November 26, 2018

RPC Contracting plans to start initial grading of the sidewalk corridor at the northern end of the project area (by Resort Realty) this week. Due to the use of heavy equipment, the southbound travel lane may be closed at times. At such times, traffic will be directed into the middle lane. Please be alert for […]

Read More