Pedestrian Plan Phase II Update- February 15, 2019

Over the past week, we’ve continued seeing the progression of the new sidewalk through Duck Village. RPC Contracting poured a lengthy stretch of sidewalk from the Waterfront Shops southward past the water tower to Kitty Hawk Kites. Additional sidewalk formwork has been installed as the project continues in a southerly direction. Duck Town Hall will […]

Read More

Pedestrian Plan Phase II Update- February 1, 2019

Over the past week we saw more rough grading work. New driveways at Kitty Hawk Kites and the southern entrance/exit to the Duck United Methodist Church were also poured. Sidewalk forms were constructed along the Waterfront Shops/Stan White Realty in preparation for pouring the first stretch of sidewalk. Additional driveway entrances have been poured in […]

Read More

Pedestrian Plan Phase II Update- December 7, 2018

Over the past week, RPC Contracting continued initial grading in the area near the Waterfront Shops and Dare County water tower. RPC Contracting will continue with initial grading of the sidewalk corridor next week moving south of the water tower.  Millstone Marine may begin construction of several bulkheads along the path of the sidewalk.  Due […]

Read More

Pedestrian Plan Phase II Update- November 9, 2018

Over the past week, RPC Contracting completed some surveying and installation of silt fencing to prevent erosion during minor grading work. These efforts will continue during the week of November 12th. Toward the end of next week, RPC could potentially begin initial grading of the sidewalk corridor at the northern end of the project area. […]

Read More

Pedestrian Plan Update- March 9, 2018

Construction on Phase I of the Town of Duck Comprehensive Pedestrian Plan along the east side of Duck Road (N.C. Highway 12) in Duck Village has been proceeding rapidly. It’s been exciting to see the final project take shape as the sidewalks are formed and poured with concrete. Over the past week, Barnhill Contracting completed […]

Read More