Pedestrian Plan Phase II Update- March 15, 2019

Over the past week, RPC Contracting poured the dumpster pad at Osprey Landing shopping center and began driveway improvements at the southern driveway to the Soundfront Shoppes.  They also backfilled landscape areas adjoining the sidewalks to improve safety and appearance in the project area.  A minimal amount of construction is anticipated during the upcoming week […]

Read More

Pedestrian Plan Phase II Update- March 8, 2019

Thanks to clear weather over the past week,  very impressive progress on the new sidewalk was made.  RPC was able to pour sidewalks in the stretch in front of Nags Head Hammocks, Duck United Methodist Church, and Wee Winks Square.  The sidewalk is now complete from the northern end of the project at Resort Realty […]

Read More

Pedestrian Plan Phase II Update- February 22, 2019

Over the past week, we’ve continued seeing of the progression of the new sidewalk through Duck Village. RPC Contracting was able to complete sidewalk formwork in several areas. However; due to the large amount of rain, they were unable to pour new sections of sidewalk.  The project continues to proceed in a southerly direction. With […]

Read More

Pedestrian Plan Phase II Update- February 15, 2019

Over the past week, we’ve continued seeing the progression of the new sidewalk through Duck Village. RPC Contracting poured a lengthy stretch of sidewalk from the Waterfront Shops southward past the water tower to Kitty Hawk Kites. Additional sidewalk formwork has been installed as the project continues in a southerly direction. Duck Town Hall will […]

Read More

Pedestrian Plan Phase II Update- February 1, 2019

Over the past week we saw more rough grading work. New driveways at Kitty Hawk Kites and the southern entrance/exit to the Duck United Methodist Church were also poured. Sidewalk forms were constructed along the Waterfront Shops/Stan White Realty in preparation for pouring the first stretch of sidewalk. Additional driveway entrances have been poured in […]

Read More

Pedestrian Plan Update- January 25, 2019

Construction work is continuing to proceed on the bicycle/pedestrian improvements along the west side of Duck Road through Duck Village despite bitter cold weather and torrential rains this week. Over the past week we saw more rough grading work and new driveways at Kitty Hawk Kites, and the southern entrance/exit to the Duck United Methodist […]

Read More

Pedestrian Plan Phase II Update- January 18, 2019

Construction work is continuing to proceed rapidly on the bicycle/pedestrian improvements along the west side of Duck Road through Duck Village. Over the past week we saw a substantial amount of construction activity with RPC Contracting continuing rough grading activities in preparation for construction along the southern portion of the project area. Millstone Marine completed […]

Read More

Pedestrian Plan Update- January 4, 2019

Construction work is well underway on the bicycle/pedestrian improvements along the west side of Duck Road through Duck Village. During the past week, Millstone Marine completed reconstruction of an older retaining wall by the Nags Head Hammocks/Duck United Methodist Church properties and preparations for the long retaining wall in front of the Town Park property. […]

Read More

Pedestrian Plan Phase II Update- December 21, 2018

The past week saw a significant increase in construction activity on the pedestrian improvements through Duck Village. RPC Contracting completed additional grading in the northern half of the project area. Millstone Marine Construction has nearly completed construction of a retaining wall by the northern end of the Duck United Methodist Church property. Millstone also began […]

Read More