Pedestrian Plan Phase II Update- June 28, 2019

Over the past week, RPC Contracting completed asphalt patches in the bike lanes, hydroseeded the bare slopes adjoining the sidewalk, and many of the items on its punch list to close-out the sidewalk project.  A final inspection will likely be conducted next week. Coinjock Farms completed the installation of ornamental grasses and other landscape materials […]

Read More

Pedestrian Plan Phase II Update- June 21, 2019

Over the past week, RPC Contracting has completed most of the items on its punch list to close-out the sidewalk project.  RPC plans to complete final grading of the swales by the Waterfront Shops/Stan White Realty early next week and have all bare areas covered with hydroseed to stabilize the slopes on Tuesday, June 25th. […]

Read More

Pedestrian Plan Phase II Update- June 7, 2019

Over the past week, RPC Contracting has made substantial progress toward the completion of the sidewalk along the west side of Duck Village.  RPC poured driveways and sidewalks from Super Wings past the Town Green to the entrance drive at Duck Town Hall.  The Town also contracted for a water meter to be relocated in […]

Read More

Pedestrian Plan Phase II Update- May 31, 2019

Over the past week, RPC Contracting has made substantial progress toward the completion of the sidewalk along the west side of Duck Village.  RPC has been forming and pouring sidewalks and driveways along the southern portion of the project. During the week of June 3rd, RPC will be forming and pouring sidewalks from Super Wings […]

Read More

Pedestrian Plan Phase II Update- May 10, 2019

Over the past week, RPC Contracting continued grading and installing the stone base in the remaining portions of the project prior to pouring sidewalks.  RPC plans to complete these preparations early next week.  By mid-week, RPC will begin installing the forms for the concrete sidewalks.  Weather permitting, RPC may begin pouring a stretch of sidewalk […]

Read More

Pedestrian Plan Phase II Update- May 3, 2019

Over the past week, RPC Contracting has completed much of the grading and site preparation for the sidewalk and driveways along the remaining southern portion of the project area.  Next week, RPC plans to continue grading and the installation of the stone base in the remaining portions of the project prior to pouring sidewalks during […]

Read More

Pedestrian Plan Phase II Update- April 26, 2019

Over the past week, RPC Contracting completed grading and site preparation for the sidewalk and driveways along the remaining southern portion of the project area.  Dominion Energy has mobilized equipment and materials in preparation for relocation of a power line running in front of Town Hall southward through the Osprey Landing Shopping Center. During the […]

Read More

Pedestrian Plan Phase II Update- April 19, 2019

During the past week, RPC Contracting completed the initial grading and trenching in the southern portion of the project area.  Next week, they will begin removing driveway entrances, one half at a time, and replacing them with a temporary gravel entrance in preparation for concrete formation in the coming weeks.   The Town has stressed the […]

Read More

Pedestrian Plan Phase II Update- April 12, 2019

This week, the pavement marking subcontractor completed the installation of the new crosswalks as well as the road markings along the bike lane for the project.   RPC Contracting returned to Duck and began grading for the sidewalk at Aqua Restaurant & Spa. They intend to continue northward to Super Wings.  Once the initial grading is […]

Read More