Pedestrian Plan Phase III Update- January 13, 2020

Over the past week, Millstone Marine Construction completed  the final retaining wall in the block between Cook Drive and Duck Deli.  This week, RPC Contracting will be regrading the area in front of this retaining wall and preparing the concrete forms for the stretch of sidewalk between Dune Road and Cook Drive.  Weather permitting, RPC […]

Read More

Phase III Pedestrian Plan Update- December 20, 2019

Over the past week, RPC Contracting poured a section of sidewalk between Sea Colony Drive and Dune Road.  They also completed many of the improvements around the crosswalk at the Barrier Island Shoppes/Sunset Grille.  Continuing to work southward, RPC has prepared the concrete forms for the stretch of sidewalk between Dune Road and Cook Drive.  […]

Read More

Phase III Pedestrian Plan Update- December 16, 2019

Although limited by weather last week, RPC Contracting was able to prepare the base for several sections of sidewalk in the northern end of the project and poured a section of sidewalk in the area south of Barrier Island Station.  Sidewalk construction will continue southward from that point during the week of December 16th. RPC […]

Read More

Phase III Pedestrian Plan Update- December 2, 2019

Last week out of respect to the many visitors and businesses in Duck for the Thanksgiving holiday, RPC Contracting only completed a small amount of work.  However, RPC remains well ahead of schedule on the third phase of the bicycle and pedestrian improvements through the northern portion of Duck Village. Over the past week, Millstone […]

Read More

Pedestrian Plan Phase III Update- November 15, 2019

Over the past week, RPC stayed well ahead of schedule on the third phase of the bicycle and pedestrian improvements through the northern portion of Duck Village.  RPC completed grading and laying the base for the landscaped areas. They also prepared forms and bases for sections of sidewalk on the flatter, northern end of the […]

Read More

Pedestrian Plan Phase III Update- October 30, 2019

The third phase of bicycle and pedestrian improvements through Duck Village has begun.  Construction will take place along the east side of Duck Road from the end of the existing sidewalk at Duck Deli northward to connect with the existing shared use path at the Ships Watch neighborhood.  Similar to prior phases, the planned improvements […]

Read More

Pedestrian Plan Phase II Update- June 28, 2019

Over the past week, RPC Contracting completed asphalt patches in the bike lanes, hydroseeded the bare slopes adjoining the sidewalk, and many of the items on its punch list to close-out the sidewalk project.  A final inspection will likely be conducted next week. Coinjock Farms completed the installation of ornamental grasses and other landscape materials […]

Read More

Pedestrian Plan Phase II Update- June 21, 2019

Over the past week, RPC Contracting has completed most of the items on its punch list to close-out the sidewalk project.  RPC plans to complete final grading of the swales by the Waterfront Shops/Stan White Realty early next week and have all bare areas covered with hydroseed to stabilize the slopes on Tuesday, June 25th. […]

Read More

Pedestrian Plan Phase II Update- June 7, 2019

Over the past week, RPC Contracting has made substantial progress toward the completion of the sidewalk along the west side of Duck Village.  RPC poured driveways and sidewalks from Super Wings past the Town Green to the entrance drive at Duck Town Hall.  The Town also contracted for a water meter to be relocated in […]

Read More