Pedestrian Plan Phase II Update- December 7, 2018

Over the past week, RPC Contracting continued initial grading in the area near the Waterfront Shops and Dare County water tower. RPC Contracting will continue with initial grading of the sidewalk corridor next week moving south of the water tower.  Millstone Marine may begin construction of several bulkheads along the path of the sidewalk.  Due […]

Read More

Pedestrian Plan Phase II Update- November 30, 2018

Over the past week, RPC Contracting completed initial grading from the northern end of the project area (Resort Realty) extending southward to the Dare County water tower. RPC Contracting will continue with initial grading of the sidewalk corridor next week moving south of the water tower. Due to the use of heavy equipment, the southbound […]

Read More

Pedestrian Plan Phase II Update- November 26, 2018

RPC Contracting plans to start initial grading of the sidewalk corridor at the northern end of the project area (by Resort Realty) this week. Due to the use of heavy equipment, the southbound travel lane may be closed at times. At such times, traffic will be directed into the middle lane. Please be alert for […]

Read More

Pedestrian Plan Phase II Update- November 9, 2018

Over the past week, RPC Contracting completed some surveying and installation of silt fencing to prevent erosion during minor grading work. These efforts will continue during the week of November 12th. Toward the end of next week, RPC could potentially begin initial grading of the sidewalk corridor at the northern end of the project area. […]

Read More

Pedestrian Plan Phase II Update- November 2, 2018

Over the past week, Albemarle Landscaping completed the initial removal of trees and vegetation along the path of the new sidewalk with remaining stumps to be ground or removed soon.  During the upcoming week of November 5th, RPC Contracting plans to begin surveying and installation of silt fencing to prevent erosion during minor grading work. […]

Read More

Phase 2 Sidewalk Construction Beginning

In preparation for construction of the second phase of bicycle and pedestrian improvements in Duck Village, RPC Contracting has informed the Town of Duck that the company plans to begin the small amount of tree and vegetation removal required for the project on October 29th. The second phase of the sidewalk project will be constructed […]

Read More

Pedestrian Plan Update- May 25, 2018

The Town of Duck is nearing completion of the first phase of pedestrian improvements along the east side of Duck Road (N.C. Highway 12).   VHB Engineering conducted a final walk-through of the project on May 24th and documented that Barnhill Contracting has successfully completed its portion of the project. Over the past week, American […]

Read More

Pedestrian Plan Update- May 18, 2018

Our daily rainstorms over the past week have delayed several projects necessary for the completion of the first phase of pedestrian improvements along the east side of Duck Road (N.C. Highway 12).   Coinjock Farms Landscaping was able to install most of its initial plantings and mulch in the gateway medians and between the new […]

Read More