Beach Nourishment Update Public Meeting

The Beach Nourishment Consultants, Coastal Planning and Engineering and Great Lakes Dredge and Dock, will make the next public meeting presentation with project updates on Thursday, June 29, 2017 at 1:00 p.m in the Paul F. Keller Meeting Hall. The meeting is open to the public and all interested parties are welcome to attend. If you are […]

Read More

Beach Nourishment Update- June 27, 2017

Due to the high volume of activity on the beach during the final stages of the project, the construction zone remains between approximately Pintail Dr. and Sprigtail Dr. All dunes have been constructed and beach access can be obtained by walking along them to the open areas on either side of the construction area. The […]

Read More

Beach Nourishment Update- June 26, 2017

The construction zone remains approximately between approximately 111 Bufflehead Rd and Pintail Dr. They have almost finished constructing the dune in this area and will open it to foot traffic as soon as possible. Thank you for your patience during these final stages! There will be a final Duck public update meeting on the project […]

Read More

Beach Nourishment Update- June 25, 2017

The construction area has been extended to between approximately 111 Bufflehead Rd and Pintail Dr. Whenever possible, beach access is available by walking along the constructed dune to the open areas. Please continue to exercise caution while on the dune in the construction zones. Thank you for your patience during the final stages of this […]

Read More

Beach Nourishment Update- June 22, 2017

The Liberty Island has completed its work in Duck! They are now heading to Kill Devil Hills to begin work there. They completed the area of beach from approximately 147 Bufflehead Dr. to the southern taper of the project just past 137 Spindrift Ln. This accounts for about a half a mile, or 2,375 feet, […]

Read More

Beach Nourishment Update- June 21, 2017

Crews are still working on the Dianne St. subline to correct a mechanical issue. The Dodge Island is making its way back to Duck to resume work, anticipated to resume later this evening. The construction zone for this area remains between approximately 113 Bufflehead Rd. and 127 Mallard Dr. GLDD is currently demobilizing the Liberty […]

Read More

Beach Nourishment Update- June 20, 2017

The Dodge and Padre Islands have completed the section of beach between the Dianne St. and Ocean Bay Blvd. sublines. All beach and accesses north of 127 Mallard Dr. are complete and open! GLDD is currently experiencing mechanical issues with the Liberty Island dredge, as well as the Dianne St. subline. They are working to […]

Read More