Pedestrian Plan Update- December 1, 2017

Construction on Phase I of the Town of Duck Comprehensive Pedestrian Plan will be picking up over the next week. Now that the Thanksgiving holiday is behind us, you will begin to see more construction activity along the east side of Duck Road through Duck Village. Scheduled to begin on Tuesday (12/5), Barnhill Contracting will continue its installation of silt fencing to prevent erosion and sedimentation as grading work continues in the project area. Barnhill also plans to begin grading and excavation work in the areas designated for retaining walls along the corridor. You may click here for more information about the planned pedestrian improvements.