Living Shoreline and Resiliency Project Update | Jan. 29

Fred Smith Company is continuing road work this week and anticipates one lane of travel as they begin to lay base layers of asphalt.  Crews will be on site 24/7 while paving is occurring, and weather dependent, they hope to complete this portion of work within 3-5 days. 

This 24/7 schedule is for the road reconstruction portion of the project, not the entire project. The completion date of the Living Shoreline and Resiliency Project is estimated to be mid-May.