Pedestrian Plan Project Updates

Pedestrian Plan Phase III Update- March 9, 2020

As we near completion of Phase 3 of the pedestrian/bicycle improvements through Duck Village, RPC Contracting is wrapping up its work on the project.  Over the past week, RPC conducted final grading and installed crosswalk markings across the intersections at Cook Drive, Dune Road, Sea Colony Drive, and Olde Duck Road.  Over the week of…

Phase III Pedestrian Plan Update- January 3, 2020

Work on the bicycle and pedestrian improvements was back underway this week.  Millstone Marine Construction continues to work on the remaining retaining wall in the block between Cook Drive and Duck Deli.  Millstone should complete this retaining wall during the coming week, weather permitting. The  stretch of concrete sidewalk from Dune Road to Cook Drive…