Pedestrian Plan Update- March 23, 2018

The Town of Duck has seen great progress toward completion of its first phase of pedestrian improvements along the east side of Duck Road (N.C. Highway 12) in Duck Village. Over the past week Barnhill Contracting finished pouring concrete for the last sections of sidewalk south of Twiddy Realty to Scarborough Lane.

Over the next couple of weeks, construction activity will be minimal as Barnhill will be repairing some irrigation systems and touching up several areas prior to final grading and stabilizing the banks adjoining the sidewalk. Barnhill plans to wait until after Easter week to begin construction of the two gateway medians in the center lane north and south of Duck Village.

While heavy construction equipment is being operated along the side of the road, there may be a traffic lane shift to the middle lane. Please be alert and drive slowly and safely as you pass through the construction area.