Pedestrian Plan Update, November 9, 2017:

Phase I of the Town of Duck Comprehensive Pedestrian Plan continues moving forward.  Barnhill Contracting recently completed survey work in preparation for the excavation and grading for the new retaining walls.  The upcoming week of November 13th will see installation of silt fencing to prevent erosion and sedimentation in the project area.  Excavation for new retaining walls and minor grading work will likely start the following week.  The contractors will leave the project area in a clean and safe condition and will not have any active construction work over the extended Thanksgiving holiday weekend.

For questions about these proposed pedestrian improvements, you can contact Director of Community Development Joe Heard at jheard@townofduck.com or Town Manager Chris Layton at clayton@townofduck.com or (252)255-1234.