Phase III Pedestrian Plan Update- December 27, 2019

Due to the holidays, work on the bicycle and pedestrian improvements was limited over the past week.  Millstone Marine Construction continued to drive pilings associated with the construction of a tall retaining wall in the block between Cook Drive and Duck Deli.  Millstone plans to complete this retaining wall during the week of December 30th.

RPC Contracting has prepared the concrete forms for the stretch of sidewalk between Dune Road and Cook Drive and plans to pour this section of sidewalk when they return to work during the week of December 30th.

Due to the use of heavy equipment, the northbound travel lane may be closed at times with traffic being stopped or diverted into the middle lane during the closures.  Please be alert for construction activity and drive slowly and safely as you travel through this area of town.

The third phase of bicycle and pedestrian improvements through Duck Village is occurring along the east side of Duck Road from the end of the existing sidewalk at Duck Deli northward to connect with the existing shared use path at the Ships Watch neighborhood.  Similar to prior phases, the planned improvements include a dedicated bike lane, landscaped bed, and sidewalk.  The project also involves the construction of retaining walls, relocation of several utilities, and installation of a handicap accessible ramp at the Sunset Grille/Barrier Island Shoppes crosswalk.

Phase III construction has an estimated completion date in March 2020, but the present pace of construction may allow for the project to be completed substantially earlier.  Once Phase III is complete, the Town of Duck will have travel lanes for bicycles and pedestrians along the entire east side of Duck Road from the northern to the southern boundaries of the Town.

For questions about the bicycle and pedestrian improvements, you can contact Director of Community Development Joe Heard at jheard@townofduck.com or (252)255-1234.