Pedestrian Plan Phase II Update- June 28, 2019

Over the past week, RPC Contracting completed asphalt patches in the bike lanes, hydroseeded the bare slopes adjoining the sidewalk, and many of the items on its punch list to close-out the sidewalk project.  A final inspection will likely be conducted next week.

Coinjock Farms completed the installation of ornamental grasses and other landscape materials along the sidewalk and bike lane. They will be watering the plants due to the lack of recent rain.

The one remaining section of sidewalk will be installed by Mancuso Development as they complete construction of the new restaurant at 1184 Duck Road.

As RPC Contracting puts its finishing touches on the project, small areas of the southbound travel lane may be closed at times with traffic directed into the middle lane. Please be alert for construction activity and drive slowly and safely as you travel through Duck Village.

For questions about these proposed pedestrian improvements, you can contact Director of Community Development Joe Heard at jheard@townofduck.com or (252)255-1234.