Pedestrian Plan Phase II Update- June 14, 2019

On Tuesday, June 11th, RPC Contracting poured the final sections of concrete at the Soundside Shoppes, Osprey Landing, Town Hall, and Kellogg Supply Company to complete the sidewalk construction project. On Wednesday, VHB Engineering and Town of Duck officials walked the entire project with RPC representatives to inspect the work completed and develop a punch-list […]