Pedestrian Plan Phase II Update – November 16

RPC Contracting plans to begin initial grading of the sidewalk corridor at the northern end of the project area (by Resort Realty) on Monday, Tuesday, and Wednesday of next week.  Due to the use of heavy equipment, the southbound travel lane may be closed at times.  At such times, traffic will be directed into the […]

Read More

Pedestrian Plan Phase II Update- November 9, 2018

Over the past week, RPC Contracting completed some surveying and installation of silt fencing to prevent erosion during minor grading work. These efforts will continue during the week of November 12th. Toward the end of next week, RPC could potentially begin initial grading of the sidewalk corridor at the northern end of the project area. […]

Read More

Pedestrian Plan Phase II Update- November 2, 2018

Over the past week, Albemarle Landscaping completed the initial removal of trees and vegetation along the path of the new sidewalk with remaining stumps to be ground or removed soon.  During the upcoming week of November 5th, RPC Contracting plans to begin surveying and installation of silt fencing to prevent erosion during minor grading work. […]

Read More

NC12 Phase II Pedestrian Improvements Advertisement for Bids

Sealed Bids for the construction of NC 12 Pedestrian Improvements – Phase II will be received, by the Town of Duck, at their office located at 1200 Duck Road, Duck, NC 27949 until 2:00 PM local time on Tuesday, September 25, 2018, at which time the Bids received will be publicly opened and read.  The […]

Read More

Pedestrian Plan Update – May 4, 2018

The first phase of pedestrian improvements along the east side of Duck Road (N.C. Highway 12) in Duck Village is close to completion.  Over the past week, Barnhill Contracting completed dozens of items on its punch list.  Significant projects included reconstruction of curbing by Kellogg Hardware’s parking area, raising and reworking a segment of sidewalk […]

Read More

Pedestrian Plan Update – April 6, 2018

The Town of Duck continues to see great progress toward completion of its first phase of pedestrian improvements along the east side of Duck Road (N.C. Highway 12) in Duck Village. Construction activity will continue to be minimal next week as Barnhill will be repairing irrigation systems early in the week. Thursday and Friday they […]

Read More

Pedestrian Plan Update, November 9, 2017:

Phase I of the Town of Duck Comprehensive Pedestrian Plan continues moving forward.  Barnhill Contracting recently completed survey work in preparation for the excavation and grading for the new retaining walls.  The upcoming week of November 13th will see installation of silt fencing to prevent erosion and sedimentation in the project area.  Excavation for new retaining […]

Read More

Pedestrian Plan Update, October 26, 2017

The first week of the sidewalk construction in Duck is complete and we saw the removal of limited tree and vegetation in order to make way for the new sidewalk. This coming week of October 30th you can expect to see the removal of several wooden retaining walls in the project area beginning at the […]