Pedestrian Plan Phase II Update- May 24, 2019

Over the past week, both Dominion Energy and RPC Contracting have made a strong push to finish work necessary for the completion of the sidewalk along the west side of Duck Village.  Dominion had crews completing the splices at each end of the new line.  RPC started forming and pouring sidewalks and driveways along the […]

Read More

Pedestrian Plan Phase II Update- May 17, 2019

Over the past week, RPC Contracting continued grading and installation of the stone base in the remaining portions of the project before pouring sidewalks. On Friday, RPC will begin installation of formwork for the sidewalks and replacement stairway at Soundfeet Shoes/Ocean Atlantic Rentals. During the week of May 20th, RPC will continue the formwork and […]

Read More

Pedestrian Plan Phase II Update- May 10, 2019

Over the past week, RPC Contracting continued grading and installing the stone base in the remaining portions of the project prior to pouring sidewalks.  RPC plans to complete these preparations early next week.  By mid-week, RPC will begin installing the forms for the concrete sidewalks.  Weather permitting, RPC may begin pouring a stretch of sidewalk […]

Read More

Pedestrian Plan Phase II Update- May 3, 2019

Over the past week, RPC Contracting has completed much of the grading and site preparation for the sidewalk and driveways along the remaining southern portion of the project area.  Next week, RPC plans to continue grading and the installation of the stone base in the remaining portions of the project prior to pouring sidewalks during […]

Read More

Pedestrian Plan Phase II Update- April 26, 2019

Over the past week, RPC Contracting completed grading and site preparation for the sidewalk and driveways along the remaining southern portion of the project area.  Dominion Energy has mobilized equipment and materials in preparation for relocation of a power line running in front of Town Hall southward through the Osprey Landing Shopping Center. During the […]

Read More

Pedestrian Plan Phase II Update- April 19, 2019

During the past week, RPC Contracting completed the initial grading and trenching in the southern portion of the project area.  Next week, they will begin removing driveway entrances, one half at a time, and replacing them with a temporary gravel entrance in preparation for concrete formation in the coming weeks.   The Town has stressed the […]

Read More

Pedestrian Plan Phase II Update- April 12, 2019

This week, the pavement marking subcontractor completed the installation of the new crosswalks as well as the road markings along the bike lane for the project.   RPC Contracting returned to Duck and began grading for the sidewalk at Aqua Restaurant & Spa. They intend to continue northward to Super Wings.  Once the initial grading is […]

Read More

Pedestrian Plan Phase II Update- April 5, 2019

The past week saw no progress toward construction of the planned sidewalk as Dominion Energy completed preparations for moving several underground lines. The upcoming week (beginning 4/8) will see more substantial progress.  RPC Contracting will begin grading for the sidewalk at Aqua Restaurant & Spa and work northward to Super Wings over the next few […]

Read More

Pedestrian Plan Phase II Update- March 29, 2019

Over the past week, RPC Contracting has sprayed grass seed to stabilize the areas adjoining the sidewalk in the northern portion of the pedestrian project and completed construction of the new dumpster enclosure at the Osprey Landing shopping center. Pending confirmation by Dominion Energy, RPC plans on beginning sidewalk grading from the Osprey Landing shopping […]

Read More