Phase III Pedestrian Plan Update – November 22, 2019

RPC Contracting remains well ahead of schedule on the third phase of the bicycle and pedestrian improvements through the northern portion of Duck Village.  Over the past week, RPC poured additional sections of sidewalk in the area south of Barrier Island Station and the new stairway on the east side of the crosswalk at the […]

Read More

Pedestrian Plan Phase III Update- November 15, 2019

Over the past week, RPC stayed well ahead of schedule on the third phase of the bicycle and pedestrian improvements through the northern portion of Duck Village.  RPC completed grading and laying the base for the landscaped areas. They also prepared forms and bases for sections of sidewalk on the flatter, northern end of the […]

Read More

Pedestrian Plan Phase III Update – November 8, 2019

The third phase of construction for bicycle and pedestrian improvements through Duck Village is off to a flying start.  RPC Contracting has completed the saw cuts for the bike lane and initial grading for the sidewalk.  RPC has also installed several of the new concrete drive entrances along the path of the future sidewalk.  In […]

Read More

Pedestrian Plan Phase III Update- October 30, 2019

The third phase of bicycle and pedestrian improvements through Duck Village has begun.  Construction will take place along the east side of Duck Road from the end of the existing sidewalk at Duck Deli northward to connect with the existing shared use path at the Ships Watch neighborhood.  Similar to prior phases, the planned improvements […]

Read More

Pedestrian Plan Phase II Update- June 28, 2019

Over the past week, RPC Contracting completed asphalt patches in the bike lanes, hydroseeded the bare slopes adjoining the sidewalk, and many of the items on its punch list to close-out the sidewalk project.  A final inspection will likely be conducted next week. Coinjock Farms completed the installation of ornamental grasses and other landscape materials […]

Read More

Pedestrian Plan Phase II Update- June 21, 2019

Over the past week, RPC Contracting has completed most of the items on its punch list to close-out the sidewalk project.  RPC plans to complete final grading of the swales by the Waterfront Shops/Stan White Realty early next week and have all bare areas covered with hydroseed to stabilize the slopes on Tuesday, June 25th. […]

Read More

Pedestrian Plan Phase II Update- June 14, 2019

On Tuesday, June 11th, RPC Contracting poured the final sections of concrete at the Soundside Shoppes, Osprey Landing, Town Hall, and Kellogg Supply Company to complete the sidewalk construction project. On Wednesday, VHB Engineering and Town of Duck officials walked the entire project with RPC representatives to inspect the work completed and develop a punch-list […]

Read More

Pedestrian Plan Phase II Update- June 7, 2019

Over the past week, RPC Contracting has made substantial progress toward the completion of the sidewalk along the west side of Duck Village.  RPC poured driveways and sidewalks from Super Wings past the Town Green to the entrance drive at Duck Town Hall.  The Town also contracted for a water meter to be relocated in […]

Read More

Pedestrian Plan Phase II Update- May 31, 2019

Over the past week, RPC Contracting has made substantial progress toward the completion of the sidewalk along the west side of Duck Village.  RPC has been forming and pouring sidewalks and driveways along the southern portion of the project. During the week of June 3rd, RPC will be forming and pouring sidewalks from Super Wings […]

Read More