Pedestrian Plan Phase II Update- June 14, 2019

On Tuesday, June 11th, RPC Contracting poured the final sections of concrete at the Soundside Shoppes, Osprey Landing, Town Hall, and Kellogg Supply Company to complete the sidewalk construction project. On Wednesday, VHB Engineering and Town of Duck officials walked the entire project with RPC representatives to inspect the work completed and develop a punch-list […]

Read More

Pedestrian Plan Phase II Update- June 7, 2019

Over the past week, RPC Contracting has made substantial progress toward the completion of the sidewalk along the west side of Duck Village.  RPC poured driveways and sidewalks from Super Wings past the Town Green to the entrance drive at Duck Town Hall.  The Town also contracted for a water meter to be relocated in […]

Read More

Pedestrian Plan Phase II Update- May 31, 2019

Over the past week, RPC Contracting has made substantial progress toward the completion of the sidewalk along the west side of Duck Village.  RPC has been forming and pouring sidewalks and driveways along the southern portion of the project. During the week of June 3rd, RPC will be forming and pouring sidewalks from Super Wings […]

Read More

Hazard Mitigation Public Meeting

The next Hazard Mitigation public meeting will take place on Thursday, June 6, 2019 from 1:00 p.m.- 2:00 p.m. at the Kill Devil Hills Commissioners Meeting Room (102 Town Hall Dr.). For more information about the Outer Banks Hazard Mitigation Plan  please visit http://www.obx-hmp.com/index.html  

Read More

Town of Duck Planning Board Goes to the Coastal Studies Institute

On May 24th, Town of Duck Planning Board members attended a workshop hosted at the Coastal Studies Institute in Wanchese, NC. The first session highlighted how faculty and students from state universities have worked with local communities to conduct research, engage in planning efforts, and design solutions for communities.  Drs. Linda D’Anna and Lindsay Dubbs […]

Read More

Pedestrian Plan Phase II Update- May 24, 2019

Over the past week, both Dominion Energy and RPC Contracting have made a strong push to finish work necessary for the completion of the sidewalk along the west side of Duck Village.  Dominion had crews completing the splices at each end of the new line.  RPC started forming and pouring sidewalks and driveways along the […]

Read More

Pedestrian Plan Phase II Update- May 17, 2019

Over the past week, RPC Contracting continued grading and installation of the stone base in the remaining portions of the project before pouring sidewalks. On Friday, RPC will begin installation of formwork for the sidewalks and replacement stairway at Soundfeet Shoes/Ocean Atlantic Rentals. During the week of May 20th, RPC will continue the formwork and […]

Read More

Pedestrian Plan Phase II Update- May 10, 2019

Over the past week, RPC Contracting continued grading and installing the stone base in the remaining portions of the project prior to pouring sidewalks.  RPC plans to complete these preparations early next week.  By mid-week, RPC will begin installing the forms for the concrete sidewalks.  Weather permitting, RPC may begin pouring a stretch of sidewalk […]

Read More

Pedestrian Plan Phase II Update- May 3, 2019

Over the past week, RPC Contracting has completed much of the grading and site preparation for the sidewalk and driveways along the remaining southern portion of the project area.  Next week, RPC plans to continue grading and the installation of the stone base in the remaining portions of the project prior to pouring sidewalks during […]

Read More