Pedestrian Plan Update- January 22, 2018

Despite losing a couple of days to our recent winter storms, significant progress has been made on Phase I of the Town of Duck Comprehensive Pedestrian Plan along the east side of Duck Road (N.C. Highway 12) in Duck Village.  Barnhill Contracting is completing initial rough excavation work north past the Wee Winks/Brindley Beach property.  […]

Read More

Pedestrian Plan Update- December 15, 2017

Construction on Phase I of the Town of Duck Comprehensive Pedestrian Plan will continue next week along the east side of Duck Road through Duck Village. Barnhill Contracting plans to install the final section of silt fencing north to Duck Deli to prevent erosion and sedimentation as grading work continues in the project area. Barnhill […]

Read More

Pedestrian Plan Update- November 17, 2017

Phase I of the Town of Duck Comprehensive Pedestrian Plan continued to see progress over the past week.  Barnhill Contracting removed a short section of the asphalt Duck Trail connecting to the shoulder of Duck Road by the Four Seasons property.  Until further notice, this area is closed to bicycle and pedestrian traffic.  This section […]

Read More

Beach Grass Planting Program

The Town of Duck seeks volunteers to participate in a new program to supplement planting in the beach nourishment area. This is a fun way to get out to the beach in the off season, develop relationships with your neighbors, and give back to your community. You don’t need to live in the nourishment area, […]

Read More

Sidewalk Construction to Begin Soon in Duck Village

Barnhill Contracting has informed the Town of Duck of the company plans to begin limited tree and vegetation removal on Monday, October 23rd in preparation for construction of Phase I of bicycle and pedestrian improvements in Duck Village. The bulk of the Phase I construction will take place over the late-Fall/Winter months, with an expected […]

Read More

Updated Beach Nourishment Project Schedule

The contractor for the Town of Duck Beach Nourishment Project, and for the Towns of Kill Devil Hills and Kitty Hawk projects, Great Lakes Dredge and Dock (GLDD), has provided an updated projected schedule for the beach nourishment work.  The construction dates for Duck, originally scheduled for April 1 to approximately June 1, 2017, is […]

Read More

Invitation to Bid for Town Crosswalk Striping Now Available

Bids are not being accepted for the install of crosswalk striping at 24 intersections along the Town of Duck shared use path and NC Highway 12. All bids must be submitted using the Bid Proposal Form furnished by the Town and received no later than 2:00 p.m. on Friday, January 20, 2017. Please click here […]

Read More

Duck Fire Receives Improved Rating Following Recent Inspection

Date Posted: April 25, 2016 Duck, NC  — North Carolina Insurance Commissioner and State Fire Marshal Wayne Goodwin released news that following the recent completion of routine inspections for the Duck Fire District, Duck Fire improved their rating from 4 to 3, effective August 1, 2016.  The inspection, conducted by officials with the Department of […]

Read More

Crosswalk Striping Project Underway

The pedestrian crosswalk striping/restriping project at certain intersections north and south of Duck Village is underway, and according to the contractor, A Parking Lot Maintenance of Manteo, NC, will be completed the week of April 11. The striping/restriping of pedestrian crosswalks is occurring across the following side streets along the Duck Trail: Ocean Bay Boulevard […]

Read More