Engineers from APTIM, our beach nourishment consultants, will be surveying along the beach today. Work is planned from the pier north to Pelican Way.
Beach Profile Survey Work Continues
Crews from coastal engineering firm APTIM will continue their beach profile surveys today, June 14. Surveyors will be on the beach in a white pickup truck and a silver Jeep. Thank you for your patience and understanding during the survey work. Please feel free to contact the Town of Duck with questions or concerns: info@townofduck.com […]
Beach Grass Planting Program
The Town of Duck seeks volunteers to participate in a new program to supplement planting in the beach nourishment area. This is a fun way to get out to the beach in the off season, develop relationships with your neighbors, and give back to your community. You don’t need to live in the nourishment area, […]
Beach Nourishment Update- June 29, 2017
That moment that we’ve all been anxiously awaiting is here…the Town of Duck Beach Nourishment project is complete! The Dodge and Padre Islands wrapped up last night and have demobilized to Kill Devil Hills. Please continue to exercise caution and patience while GLDD work as quickly as possible to remove equipment from the beach, which […]
Beach Nourishment Update- June 28, 2017
The Dodge and Padre Islands continue pumping south and anticipate completion of Duck this evening! There is still a lot of activity on the beach with the current closure between approximately 129 Bufflehead and Pintail Dr. Please continue to exercise caution around this zone. The beach looks amazing and we would like to send out […]
Beach Nourishment Update- June 27, 2017
Due to the high volume of activity on the beach during the final stages of the project, the construction zone remains between approximately Pintail Dr. and Sprigtail Dr. All dunes have been constructed and beach access can be obtained by walking along them to the open areas on either side of the construction area. The […]
Beach Nourishment Update- June 26, 2017
The construction zone remains approximately between approximately 111 Bufflehead Rd and Pintail Dr. They have almost finished constructing the dune in this area and will open it to foot traffic as soon as possible. Thank you for your patience during these final stages! There will be a final Duck public update meeting on the project […]
Beach Nourishment Update- June 25, 2017
The construction area has been extended to between approximately 111 Bufflehead Rd and Pintail Dr. Whenever possible, beach access is available by walking along the constructed dune to the open areas. Please continue to exercise caution while on the dune in the construction zones. Thank you for your patience during the final stages of this […]
Beach Nourishment Update- June 24, 2017
The new construction area for the project is between approximately 111 Bufflehead Rd. and Wood Duck Dr.