Project Status and Updates

This page will display construction updates.

**Beach nourishment construction is dependent on a number of factors including weather, mechanical issues, and other unforeseen delays.

Expected Beach Nourishment Schedule | 2022

Weeks Marine expects to nourish Duck’s project on the following schedule:

Estimated Equipment Staging*Estimated Construction Start Date*Estimated Project Duration*
August 2022 Mid-September 202220-30 days
*This schedule is tentative and subject to change based on a number of factors.*

To follow the progress as construction moves north from Kill Devil Hills, visit MoreBeachToLove.com to find updates on all Dare County beach nourishment projects.