This page will display construction updates.
**Beach nourishment construction is dependent on a number of factors including weather, mechanical issues, and other unforeseen delays.
Beach Nourishment Update | March 23, 2023
Weeks Marine installed the subline on March 21, 2023 and is planning to begin work in Duck on April 10. They will be moving equipment after next week but will not be moving on the beach over Easter weekend.
Weeks Marine expects that they will be able to complete nourishment and have all equipment removed from the beach before Memorial Day.
Updates will continue to be shared as they are received. Please note that this is tentative and subject to change based on several factors.
For more information, please visit https://www.townofduck.com/beach-nourishment-project/.
Beach Nourishment Update | March 20, 2023
Weeks Marine has installed the matting in preparation for landing the subline on Tuesday, March 21, 2023. They expect to begin pumping on April 1.
Updates will continue to be shared as they are received. Please note that this is tentative and subject to change based on several factors.
For more information, please visit https://www.townofduck.com/beach-nourishment-project/.
Beach Nourishment Update | March 17, 2023
Weeks Marine is anticipating that they will begin mobilization on Monday, March 20th with subline installation occurring on Tuesday, March 21st. They expect to begin pumping on April 1, 2023.
Please note that this is tentative and subject to change based on several factors.
For more information, please visit https://www.townofduck.com/beach-nourishment-project/.
Beach Nourishment Update | March 8, 2023
Weeks Marine has reported a shipyard delay and is expecting to start pumping sand on April 1, 2023.
They expect to begin mobilization via Southern Shores around March 20, 2023 and they will continue to work on landing the subline in the next couple of weeks.
Please note that this is tentative and subject to change based on several factors.
For more information, please visit https://www.townofduck.com/beach-nourishment-project/.
Beach Nourishment Update March 6, 2023
Due to the weather forecast this week, Week’s Marine does not expect to install the subline in Duck this week.
They will continue monitoring the weather and updates will be posted as they become available.
BEACH NOURISHMENT SCHEDULE UPDATE | NOVEMBER 22
We have been informed by Weeks Marine, the contractor doing the four- town beach nourishment project, that they are likely to be delaying work in Duck until mid- March. Due to equipment issues, minor weather- related delays, and commitment to
another time- sensitive job, Weeks Marine has fallen behind the original schedule.
Dare County, with whom this contract is made, and our coastal engineers, Weeks Marine staff members, and our team are working on a contract modification to ensure that our project is properly constructed in the spring. This will include assurances that any beach/ dune losses between now and when the project is completed are properly replaced and that Weeks Marine will be responsible for all costs associated with additional sand and delays.
This change in schedule, while unfortunate, will have beach nourishment completed before the busier time of year and after the typically heavier part of the winter storm season. We remain confident that the job will be completed according to the new schedule by no later than mid- May.
For more information on the project please visit our More Beach to Love website.