Due to weather, the dredge is now expected back onsite tomorrow afternoon, Monday, May 1.
The active construction zone is located between Pintail Drive and North Snow Geese Drive. The completed section is between Whistling Swan Drive and Skimmer Way, however the completed section between Pintail Drive and Whistling Swan Drive is currently closed. Please obey all posted signage in these areas and remember that all schedules are subject to change.
For more information, please visit: https://www.townofduck.com/beach-nourishment-project/