Beach Nourishment Schedule Update | August 3, 2022

Weeks Marine has released an updated schedule for the beach nourishment project under construction from Kill Devil Hills to Duck.

At this time, the company anticipates work in Duck to begin on or around November 4 and conclude in early December.